Manually Flange Facer work on Vessel
Manually mini facer show how convenience it is, for flange size:1 07"-14" Type: Internal mounted
6″-40″ Flange facing machine at workshop
Due to the installation problem, customer have to refacing the flange after welding, various size of flanges...
6″-40″ Flange facing machine at Chemcial Plant – China
When the client called me said can not cut SS316, it was already 11:00 midnight on August 4th
Flange facing Machine Applied in Middle East
A flange refacing job at Damman, Saudi Arabia, Client: ARAMCO, ID-mounted flange faceing machine....
High pressure steam pipeline for ethylene plant
Zhejiang Petrochemical Phase II Project, located in Zhoushan, Ningbo It is a new project of 40 Million Tons per
Training @ Olayan Descon-Damman, Saudi Arabia
Suppy the demonstrations and training are our basic services, in the Damman-Saudi Arabia...
120mm walled pipe – Maintenance job at Power plant
This project is not easy to do But the contractor show the professional operation, 120mm wall thick ...
Heavy-walled pipe beveling At SANY Group
Machine size: 8 "-14 ",Driven: Hydraulic Operated Pipe size: 10 "x40mm beveling and counterboring...
Turkey Project: 40″ Pipeline Maintainance
Project: Sectional replacement of 36" pipeline in Turkey, the split frame machine size 36"-42" ...
Gas Pipe shutdown maintain- DANA gas, Iraq
NODHA Iraq client get this field of project. Safety is always first. Every clients must implement safety rules.
40 Million Tons Project: Diesel hydrocracking unit
This is an ongoing project owned by Sinopec, located in Zhoushan, Ningbo It is a new project of 40 Million Tons
HNEC Pipeline Maintenance In Middle of China
July 10th, In Middle of China for trainning the cold cutting of pipe with 3mm 825 incoloy cladding